SOCIETY | 12:34 / 17.11.2019
874
1 min read

Epsilon joinly with Uzbekneftegaz expands gas pipeline network

Photo: Epsilon

As of November 17, 13.100 t (80.7 km) of pipes were shipped and 9.200 t (56 km) were delivered; 15.4 km of trenches were dug, 16.2 km of pipes were welded into a string and 1.4 km of pipes were laid.

Over the past day, 2.6 km of pipes were welded, 1.000 m of trenches were dug and 1.400 t (8.5 km) of pipes were shipped. The company plans to construct 4 km of gas pipelines per day, starting from November 21, 2019.

Epsilon will keep the readers updated on the progress of construction.

Epsilon Press Office

Related News