On November 25, after hydraulic fracturing at three wells of Janubiy Tandircha and Samantepe fields, the total daily flow rate increased from 362,000 to 530,000 m³ of gas.

The daily production rate of Janubiy Tandircha-47 well reached 180,000 m³.

The flow rate of Samantepe-76 well increased to 100,000 m³ per day.

The production rate of Janubiy Tandircha-30 reached 250,000 m³ per day.

Construction of gas pipelines continues.

As of November 25, 19,100 t (113.6 km) of pipes were shipped and 11,900 t (72.9 km) were delivered; 30.1 km of trenches were dug, 44.3 km of pipes were welded into a string and 4.8 km were laid.

Over the past day, 4.4 km of trenches were dug, 4.4 km of pipes were welded and 1,300 m were laid.

Epsilon will keep informing the readers about its undertakings.

EPSILON Press Office