18:15 / 02.12.2019
917

EPSILON: Developing gas pipeline infrastructure in cooperation with Uzbekneftegaz

Photo: Epsilon

Over the past day, 1,300 t of pipes were shipped, 2.4 km of trenches were dug, 800 m of pipes were welded and 600 m were laid. In addition, 2.3 km of pipes were delivered to the location of “Tandircha CP - Shurtanneftegaz” and 700 m – to “Chigil CP - Mubarek GPP”.

In parallel with construction of “Nazarkuduk CP - Shurtanneftegaz” line, the company began laying two more pipelines: “Tandircha CP - Shurtanneftegaz” and “Chigil CP - Mubarek GPP”. As of December 2, 24,300 t of pipes were shipped and 17,300 t were delivered; 49.4 km of trenches were dug, 61.3 km of pipes were welded and 8.6 km were laid.

Round-the-clock works are ahead of schedule. Pipeline construction speed is 4 km per day. The first string of “Nazarkuduk CP - Shurtanneftegaz” pipeline will be completed on December 3.

Epsilon will continue updating the readers on the progress of its undertakings.

EPSILON Press Office

Top