EPSILON: Developing gas pipeline infrastructure in cooperation with Uzbekneftegaz
Over the past day, 1,300 t of pipes were shipped, 2.4 km of trenches were dug, 800 m of pipes were welded and 600 m were laid. In addition, 2.3 km of pipes were delivered to the location of “Tandircha CP - Shurtanneftegaz” and 700 m – to “Chigil CP - Mubarek GPP”.
In parallel with construction of “Nazarkuduk CP - Shurtanneftegaz” line, the company began laying two more pipelines: “Tandircha CP - Shurtanneftegaz” and “Chigil CP - Mubarek GPP”. As of December 2, 24,300 t of pipes were shipped and 17,300 t were delivered; 49.4 km of trenches were dug, 61.3 km of pipes were welded and 8.6 km were laid.
Round-the-clock works are ahead of schedule. Pipeline construction speed is 4 km per day. The first string of “Nazarkuduk CP - Shurtanneftegaz” pipeline will be completed on December 3.
Epsilon will continue updating the readers on the progress of its undertakings.
EPSILON Press Office
Related News
08:56 / 29.10.2022
EPSILON (EDC): Karakara-1 well produces 120,000 m³ of gas per day
09:48 / 25.10.2022
EPSILON (EDC): Daily production rate of Kirkkuloch-4 well reached 50,000 m³ of gas
08:30 / 20.10.2022
EPSILON (EDC): Production rate of Yangiarik-1 well amounted to 8 t of oil per day
19:53 / 30.07.2022