Round-the-clock construction of "Chigil CP - Mubarek GPP" gas pipeline is in progress.
Total for January 27:
- 131,600 t of pipes shipped;
- 91,100 t of pipes arrived;
- 161.2 km of trenches dug;
- 217.3 km of pipes welded;
- 126.3 km laid.
EPSILON Press Office





