EPSILON: Developing unified gas supply system in cooperation with Uzbekneftegaz

Photo: EPSILON
Round-the-clock construction of "Chigil CP - Mubarek GPP" gas pipeline is in progress.
Total for January 27:
- 131,600 t of pipes shipped;
- 91,100 t of pipes arrived;
- 161.2 km of trenches dug;
- 217.3 km of pipes welded;
- 126.3 km laid.
EPSILON Press Office
Recommended
List of streets and intersections being repaired in Tashkent published
SOCIETY | 19:12 / 16.05.2024
Uzbekistan's flag flies high on Oceania's tallest volcano
SOCIETY | 17:54 / 15.05.2024
New tariffs to be introduced in Tashkent public transport
SOCIETY | 14:55 / 05.05.2023
Onix and Tracker cars withdrawn from sale
BUSINESS | 10:20 / 05.05.2023
Latest news
-
Belarusian MTZ launches tractor assembly plant in Uzbekistan
SOCIETY | 13:39
-
Master’s admissions open: Language proficiency certificates required
SOCIETY | 13:26
-
Uzbekistan looks to ease visa process for Canada, Argentina, and Australia
SOCIETY | 13:19
-
Saida Mirziyoyeva joins jury of Zayed Award for Human Fraternity
POLITICS | 12:57
Related News

10:55 / 15.11.2022
EPSILON (EDC): Daily production rate of Karakara-2 well amounted to 100,000 m³ of gas

15:44 / 27.10.2022
EPSILON (EDC): Production rate of Ernazar-12 well amounted to 50,000 m³ of gas per day

10:43 / 23.10.2022
EPSILON (EDC): Production rate of Nazarkuduk-3 well amounted to 150,000 m³ of gas per day

20:51 / 21.10.2022