EPSILON in cooperation with Uzbekneftegaz intensifies production of gas and construction of pipelines
On November 25-26, fracking operations were conducted at three wells of Koratepa, Kirkchashma and Bokhoriston fields. The company expects industrial inflow of gas.
Construction of pipelines:
As of November 26, 20,900 t (122.6 km) of pipes were shipped and 12,100 t (73.7 km) were delivered; 31.1 km of trenches were dug, 47.8 km of pipes were welded into a string and 5.5 km were laid.
Over the past day, 1,800 t (9 km) of pipes were shipped, 200 t (800 m) were delivered, 1,000 m of trenches were dug, 3.5 km of pipes were welded and 700 m were laid.
All produced gas is routed to the domestic market to cover the needs of Uzbekistan’s population.
Epsilon will continue informing the readers on its undertakings.
EPSILON Press Office
Related News
08:56 / 29.10.2022
EPSILON (EDC): Karakara-1 well produces 120,000 m³ of gas per day
09:48 / 25.10.2022
EPSILON (EDC): Daily production rate of Kirkkuloch-4 well reached 50,000 m³ of gas
08:30 / 20.10.2022
EPSILON (EDC): Production rate of Yangiarik-1 well amounted to 8 t of oil per day
19:53 / 30.07.2022