BUSINESS | 18:36 / 19.12.2019
979
1 min read

EPSILON: Increasing production of hydrocarbons in cooperation with Uzbekneftegaz to supply the population during winter

On December 19, following successful fracking at Qumli-22 and Kulbishkek-48 wells, their total daily flow rate reached 160,000 m³ of gas.

The production rate of Qumli-22 well increased from 0 to 60,000 m³ of gas per day.

The flow rate of Kulbishkek-48 well increased from 40,000 to 100,000 m³ of gas per day.

Round-the-clock construction of gas pipelines continues:

  • “Tandircha CP – Shurtanneftegaz” (45 km);
  • “Chigil CP – Mubarek GPP” (110 km);
  • “Talimarjon CP – Shurtanneftegaz” (8 km).

Total for December 19:

  • 46,200 t of pipes shipped;
  • 29,700 t of pipes arrived;
  • 91.3 km of trenches dug;
  • 117.2 km of pipes welded into a string;
  • 75.9 km laid.

EPSILON Press Office

Related News