19:00 / 03.02.2020
1049

EPSILON (EDC): Implementing gas transmission infrastructure development projects in cooperation with Uzbekneftegaz

Round-the-clock construction of “Chigil CP – Mubarek GPP” gas pipeline continues.

Total for February 3:

  • 145,400 t of pipes shipped;
  • 111,100 t of pipes arrived;
  • 183.3 km of trenches dug;
  • 223.6 km of pipes welded into a string;
  • 127.6 km laid.

Epsilon Development Company (EDC) Press Office

Top