The “Yuksalish” Movement has conducted a public monitoring initiative to assess the implementation of Uzbekistan’s 2024 targets related to drinking water and sewerage supply. The findings reveal serious discrepancies between official reports and actual progress. Out of 100 surveyed neighborhoods, work in 23 was found incomplete despite being marked “completed” in official documents. Additionally, 28 projects were not delivered on time, 15 neighborhoods still lack full access to water services, and 9 projects were executed with poor quality.
Ambitious goals, flawed execution
According to a presidential decree, 1.3 trillion UZS was allocated from the national budget in 2024 to fund 79 projects. These aimed to construct 1,100 km of pipelines and 64 water infrastructure facilities across 200+ neighborhoods, raise the centralized drinking water supply coverage to 81%, provide clean water to 1.3 million citizens, and improve supply conditions for 3 million more.
The “Yuksalish” Movement reviewed 99 such projects in 101 neighborhoods across Uzbekistan, analyzing efforts financed through the national and local budgets and international financial institutions. They also collected local residents’ opinions on water and sewerage services.
Key Findings:
Officially “completed” but actually incomplete
Out of the 67 projects claimed by Uzsuvtaminot JSC to be complete, 23 had unfinished construction, reconstruction, or repair work. For example:
- In Ergashobod and Olaqanot neighborhoods of Asaka District, and Bobojon in Shahrihon District, construction work was left incomplete.
Not delivered on time
28 projects were either delayed or handed over before full completion. Examples include:
- In the “Farovon” Street of the “New Uzbekistan” neighborhood in Chust District (Namangan region), sewer installations for new multi-story housing blocks remain unfinished.
- In the “Al-Khorezmi” residential complex in Urgench (Khorezm), homes were handed over without completing sewer network construction.
- In Gulistan (Syrdarya), although networks in Bakht, Istiqlol, and Ahillik were built and “delivered,” the sewer system was never activated.
Poor quality work
9 projects were found to be of substandard quality. For example: