EPSILON: Round-the-clock pipeline construction works continue

Photo: EPSILON
In cooperation with Uzbekneftegaz the company develops gas transportation infrastructure and implements a project on laying "Chigil CP - Mubarek GPP" pipeline.
Total for January 26:
- 127,900 t of pipes shipped;
- 87,400 t of pipes arrived;
- 160.2 km of trenches dug;
- 215.7 km of pipes welded;
- 126.3 km laid.
EPSILON Press Office
Recommended
List of streets and intersections being repaired in Tashkent published
SOCIETY | 19:12 / 16.05.2024
Uzbekistan's flag flies high on Oceania's tallest volcano
SOCIETY | 17:54 / 15.05.2024
New tariffs to be introduced in Tashkent public transport
SOCIETY | 14:55 / 05.05.2023
Onix and Tracker cars withdrawn from sale
BUSINESS | 10:20 / 05.05.2023
Latest news
-
High spending and shady contracts: Anti-Corruption Agency launches probe into Khanabad music festival
BUSINESS | 22:25 / 26.07.2025
-
Soaring gasoline prices and consumer rights issues spark debate in Uzbekistan
POLITICS | 19:50 / 26.07.2025
-
Tashkent’s master plan open to revision, but not for private interests – Ministry of Construction
POLITICS | 18:47 / 26.07.2025
-
Bilol’s Motors director on trial for defrauding 48 customers in UZS 13 billion scheme
SOCIETY | 17:52 / 26.07.2025
Related News

10:55 / 15.11.2022
EPSILON (EDC): Daily production rate of Karakara-2 well amounted to 100,000 m³ of gas

15:44 / 27.10.2022
EPSILON (EDC): Production rate of Ernazar-12 well amounted to 50,000 m³ of gas per day

10:43 / 23.10.2022
EPSILON (EDC): Production rate of Nazarkuduk-3 well amounted to 150,000 m³ of gas per day

20:51 / 21.10.2022