BUSINESS | 13:55 / 15.11.2019
725
1 min read
Epsilon: Pipeline construction in cooperation with Uzbekneftegaz continues
As of November 15, 2019, 1.4 km of pipes were laid, 11.2 km were welded and 13.6 km of trenches were dug; 7,900 t of pipes (48 km) arrived and 11,700 t (72.2 km) were shipped.
Over the past day, additional 1.8 km of pipes were welded and 1.6 km of trenches were dug.
To supply the population with natural gas during the autumn-winter period, the companies started construction of two double-line pipelines: “Nazarkuduk AP – Shurtanneftegaz” (67 km) and “Chigil AP – Mubarek GPP” (110 km). These will be transporting gas to the processing facilities.
Epsilon will keep the readers updated on the progress of construction.
Epsilon Press Office
Related News
08:56 / 29.10.2022
EPSILON (EDC): Karakara-1 well produces 120,000 m³ of gas per day
09:48 / 25.10.2022
EPSILON (EDC): Daily production rate of Kirkkuloch-4 well reached 50,000 m³ of gas
08:30 / 20.10.2022
EPSILON (EDC): Production rate of Yangiarik-1 well amounted to 8 t of oil per day
19:53 / 30.07.2022