As of November 18, 13.100 t (80.7 km) of pipes were shipped and 9.200 t (56 km) were delivered; 16.4 km of trenches were dug, 19.6 km were welded into a string and 3.1 km of pipes were laid.
Over the past day, 3.4 km of pipes were welded, 1.000 m of trenches were dug and 1.7 km of pipes were laid. Epsilon plans to construct 4 km of pipelines per day, starting from November 21.
The company will continue informing readers on the progress of construction works.
Epsilon Press Office