BUSINESS | 12:40 / 21.11.2019
873
2 min read

Epsilon in cooperation with Uzbekneftegaz increases production of hydrocarbons

On November 20-21, following hydraulic fracturing, gas inflow was obtained from three wells of Janubiy Tandircha field. The total daily production rate increased from 350,000 to 550,000 m³.

After fracking, the daily flow rate of Janubiy Tandircha-27 reached 180,000 m³ of gas.

After fracking at Janubiy Tandircha-57, its daily production rate increased to 200,000 m³ of gas.

After fracking at Janubiy Tandircha-32, its daily flow rate reached 170,000 m³ of gas.

Construction of gas pipelines continues

As of November 21, 16,200 t (98.1 km) of pipes were shipped and 10,000 t (60.8 km) were delivered; 20 km of trenches were dug, 30.3 km of pipes were welded into a string and 3.5 km of pipes were laid.

The construction will be completed on December 6, 2019.

Epsilon will continue updating the readers on its undertakings.

EPSILON Press Office

Related News