BUSINESS | 08:30 / 25.11.2019
927
1 min read
Epsilon jointly with Uzbekneftegaz expands gas pipeline network
As of November 24, 19,100 t (113.6 km) of pipes were shipped and 11,900 t (72.9 km) were delivered; 25.7 km of trenches were dug, 40.9 km of pipes were welded into a string and 3.5 km were laid.
Over the past day, 500 t (3.1 km) of pipes were shipped, 3.5 km of trenches were dug and 3.5 km of pipes were welded.
Construction of gas pipelines will be completed on December 6, 2019.
Epsilon will continue informing the readers on its undertakings.
EPSILON Press Office