Epsilon jointly with Uzbekneftegaz increases production of natural gas

On November 25, after hydraulic fracturing at three wells of Janubiy Tandircha and Samantepe fields, the total daily flow rate increased from 362,000 to 530,000 m³ of gas.
The daily production rate of Janubiy Tandircha-47 well reached 180,000 m³.
The flow rate of Samantepe-76 well increased to 100,000 m³ per day.
The production rate of Janubiy Tandircha-30 reached 250,000 m³ per day.
Construction of gas pipelines continues.
As of November 25, 19,100 t (113.6 km) of pipes were shipped and 11,900 t (72.9 km) were delivered; 30.1 km of trenches were dug, 44.3 km of pipes were welded into a string and 4.8 km were laid.
Over the past day, 4.4 km of trenches were dug, 4.4 km of pipes were welded and 1,300 m were laid.
Epsilon will keep informing the readers about its undertakings.
EPSILON Press Office
- Tags:
- #Epsilon
Related News

18:48 / 11.12.2019
EPSILON: Developing gas pipeline infrastructure in Kashkadarya region in cooperation with Uzbekneftegaz

18:46 / 10.12.2019
EPSILON: Increasing production of natural gas and expanding pipeline network in cooperation with Uzbekneftegaz

18:35 / 09.12.2019
EPSILON: Expanding Kashkadarya gas pipeline network in cooperation with Uzbekneftegaz
Ушбу хабарга ўз фикрингизни билдиринг. Фикр билдириш учун авторизациядан ўтишингиз керак!
Authorization with social networks