EPSILON: Increasing oil production and expanding gas pipeline network in cooperation with Uzbekneftegaz

On November 29, after hydraulic fracturing, the daily production rate of two wells at Kukdumalok field increased from 9.8 to 35 t of oil.

On November 28-29, fracking operations were conducted at three wells of Koratepa, Kirkchashma and Chulkuvar fields. Industrial flow of gas is expected.

Pipeline construction continues

Over the past day, 600 t (2.2 km) of pipes were shipped and 1,400 t (6.4 km) were received; 1,400 m of trenches were dug, 3.5 km of pipes were welded into a string and 600 m were laid.

 

As of November 29, 22,600 t (129.6 km) of pipes were shipped and 15,900 t (95.0 km) were delivered; 37.2 km of trenches were dug, 58.0 km of pipes were welded and 7.5 km were laid.

The company will keep informing the readers about its undertakings.

EPSILON Press Office