On December 12, following hydraulic fracturing, the daily flow rate of Garbiy Toylok-25 well increased from 0 to 50,000 m³ of gas.
In line with the government’s decision, extracted hydrocarbons are routed to the population.
Pneumatic testing of “Nazarkuduk CP – Shurtanneftegaz” pipeline (67 km) is underway. Round-the-clock construction of two gas pipelines continues: “Tandircha CP – Shurtanneftegaz” (45 km) and “Chigil CP – Mubarek GPP” (110 km).
Total for December 12:
- 36,000 t of pipes shipped;
- 23,600 t of pipes arrived;
- 64.6 km of trenches dug;
- 96.2 km of pipes welded;
- 58.4 km laid.
EPSILON Press Office