EPSILON: Commencing gas transportation via new “Nazarkuduk CP – Shurtanneftegaz” pipeline and increasing hydrocarbon production in cooperation with Uzbekneftegaz
On December 14, following hydraulic fracturing, the daily flow rate of three wells at Khoja-Khairam and Garbiy Toylok fields reached 140,000 m3 of gas.
The production rate of Khoja-Khairam-5 well increased from 0 to 50,000 m³ of gas per day.
The flow rate of Garbiy Toylok-11 well increased from 0 to 50,000 m³ of gas per day.
The production rate of Garbiy Toylok-12 well increased from 0 to 40,000 m³ of gas per day.
After successful pneumatic testing, “Nazarkuduk CP – Shurtanneftegaz” gas pipeline (67 km) was commissioned.
Round-the-clock construction of two gas pipelines continues:
· “Tandircha CP – Shurtanneftegaz” (45 km);
· “Chigil CP – Mubarek GPP” (110 km).
Total for December 14:
· 37,900 t of pipes shipped;
· 24,900 t of pipes arrived;
· 71.4 km of trenches dug;
· 100.8 km of pipes welded into a string;
· 65.3 km laid.
EPSILON Press Office
Related News
08:56 / 29.10.2022
EPSILON (EDC): Karakara-1 well produces 120,000 m³ of gas per day
09:48 / 25.10.2022
EPSILON (EDC): Daily production rate of Kirkkuloch-4 well reached 50,000 m³ of gas
08:30 / 20.10.2022
EPSILON (EDC): Production rate of Yangiarik-1 well amounted to 8 t of oil per day
19:53 / 30.07.2022