EPSILON: Developing gas transportation infrastructure in Kashkadarya in cooperation with Uzbekneftegaz
Round-the-clock construction of three gas pipelines continues: “Tandircha CP – Shurtanneftegaz” (45 km), “Chigil CP – Mubarek GPP” (110 km), “Talimarjon CP – Shurtanneftegaz” (8 km).
Total for December 20:
- 49,100 t of pipes shipped;
- 30,200 t of pipes arrived;
- 93.4 km of trenches dug;
- 119.2 km of pipes welded;
- 75.9 km laid.
EPSILON Press Office