EPSILON: Increasing hydrocarbon production and expanding gas pipeline network in cooperation with Uzbekneftegaz
On January 8, following hydraulic fracturing at three wells of Doya Khatun field, their total daily flow rate reached 280,000 m³ of gas.
The flow rate of Doya Khatun-6 well increased from 0 to 80,000 m³ of gas per day.
The production rate of Doya Khatun-17 well increased from 60,000 to 100,000 m³ of gas per day.
The daily flow rate of Doya Khatun-58 well increased from 55,000 to 100,000 m³ of gas.
Construction of “Chigil CP – Mubarek GPP” gas pipeline continues.
As of January 8:
- 80,000 t of pipes shipped;
- 55,800 t of pipes arrived;
- 118.6 km of trenches dug;
- 152.9 km of pipes welded;
- 117.5 km laid.
EPSILON Press Office
Related News
08:56 / 29.10.2022
EPSILON (EDC): Karakara-1 well produces 120,000 m³ of gas per day
09:48 / 25.10.2022
EPSILON (EDC): Daily production rate of Kirkkuloch-4 well reached 50,000 m³ of gas
08:30 / 20.10.2022
EPSILON (EDC): Production rate of Yangiarik-1 well amounted to 8 t of oil per day
19:53 / 30.07.2022