BUSINESS | 16:43 / 10.01.2020
686
1 min read
EPSILON: Increasing production and expanding gas pipeline network in cooperation with Uzbekneftegaz
On January 10, after fracking at Doya Khatun-65 well, its daily flow rate increased from 75,000 to 120,000 m³ of gas.
Round-the-clock construction of “Chigil CP – Mubarek GPP” pipeline is in progress.
Total for January 10:
- 81,400 t of pipes shipped;
- 62,000 t of pipes arrived;
- 118.6 km of trenches dug;
- 161.9 km of pipes welded;
- 117.5 km laid.
EPSILON Press Office