EPSILON (EDC): Increasing production rate of Ayzavat-8 well to 100,000 m³ of gas per day
On November 28, 2022, EDC obtained an industrial inflow of gas at well No.8, Ayzavat field, Kashkadarya region, having completed recovery works that included cement plug placing.
Later today, the well will be connected to the main pipeline and begin supplying natural gas to the domestic market. The operations comply with relevant sanitary-epidemiological and environmental requirements.