BUSINESS | 21:33 / 22.11.2019
803
2 min read

EPSILON: Increasing natural gas production in cooperation with Uzbekneftegaz

On November 21-22, after hydraulic fracturing, gas inflow was obtained from three wells of Janubiy Tandircha and Samantepe fields. The total daily flow rate increased from 287,000 to 490,000 m³.

The flow rate of Janubiy Tandircha–81 reached 200,000 m³ per day.

The production rate of Janubiy Tandircha–49 reached 150,000 m³ per day.

The flow rate of Samantepe–84 reached 140,000 m³ per day.

Construction of gas pipelines continues. 

Over the past day, 1,800 t (9.5 km) of pipes were shipped and 1,900 t (12.1 km) were delivered; 1,600 m of trenches were dug and 4.1 km of pipes were welded into a string.

As of November 22, 18,000 t (107.6 km) of pipes were shipped and 11,900 t (72.9 km) were delivered; 21.6 km of trenches were dug, 34.4 km of pipes were welded and 3.5 km of pipes were laid.

The construction will be completed on December 6, 2019.

Epsilon will keep informing the readers on its undertakings.

EPSILON Press Office

Related News