Customers of Marat Khayrullaevich, who sells apartments under the brand name “Imarat Development,” have voiced strong complaints. A number of his projects attracted hundreds of buyers thanks to low prices and flexible payment terms. However, disputes between clients and the company soon began to emerge. The main reason was the company’s practice of withholding a penalty of 10–12 percent of the apartment’s total value from citizens who wanted to cancel contracts for unfinished apartments.

Kun.uz decided to look into another “new building” controversy after receiving numerous complaints. Among them, the cases related to “Imarat Development” and its head, Marat Khamdamov, stood out.

Buyers said they either had already terminated or were seeking to terminate their contracts with the company for various reasons. Yet doing so has proved costly. The contracts stipulate that if the buyer cancels before the property is handed over, the developer retains 10–12 percent of the total apartment price – not the amount actually paid.

For example, if a buyer signs a contract worth UZS 400 million and has paid UZS 120 million in installments, canceling the contract would mean losing UZS 40–48 million. The penalty is calculated from the UZS 400 million contract value, not from the UZS 120 million already paid.

One client, Umaraliyeva, said she purchased an apartment for UZS 350 million in the Sergeli City project in 2024 and had already paid UZS 166 million. After an inspection by the construction authority, she decided to terminate the contract. The company deducted 10 percent of the contract’s total value as a penalty.

“By the time I applied to cancel, I had already paid UZS 166 million. The documents for block A10 were not in order, the location was far away – though we agreed to that – and construction was progressing very slowly. When I asked for my money back, they withheld UZS 35 million, not from what I had paid but from the full apartment price. For two years they used our money, then deducted a penalty. They even told me that unless I agreed to forgo the penalty, they would not return the funds at all. Later, the Ministry of Construction found that drainage and concrete works were of poor quality and that my block had document issues,” she said.

Another buyer, Ziyoda Ochilova, said she had paid nearly UZS 134 million for a one-room, 20-square-meter apartment in the Tuzel Park project. But as construction never began, she went to cancel the contract. According to her, the company lawyer refused to accept her application.